Signature Villas and Garden Homes
Background
The Fronds of Palm Jebeli Ali will be the site for approximately 393 Signature Villas and 1345 Garden Homes that enjoy beach frontages that over look the waters of the palm.
Construction Process
Step 1 – 40% of total work
• Reclamation, soil improvement and breakwaters (key element of the development enabling the rest of the project to start).
Step 2 – 30% of total work
• Infrastructure works which includes:
1. Main utility services (electricity, water, sewage, telecom and gas).
2. Main bridges and roads.
3. Retaining walls.
Step 3 – 30% of total work
• Works within plots:
1. Villas
2. Pool
3. Landscaping
Most Recent Updates
Step 1
• All reclamation and soil improvement works to enable construction of the committed villas is completed.
Step 2
• On Frond A & P main utility works in progress.
• The Bridge connecting Palm Jebel Ali Trunk with Spine started and scheduled for completion by April 2009.
Step 3
• Design is completed.
• 6 mock-up villas are in progress, scheduled completion by 2009.
• Construction of Signature Villas & Garden Homes is scheduled for completion no latter than December 2012. |