Palm Jebel Ali Town Houses
Background
The Town Houses of Palm Jebel Ali are located on coves of the fronds which provide each property sea view with a spacious section of waterfront.
Construction Process
Step 1 – 40% of total work
• Reclamation, soil improvement and breakwaters (key element of the development enabling the rest of the project to start).
Step 2 – 30% of total work
• Infrastructure works which includes:
1. Main utility services (electricity, water, sewage, telecom and gas).
2. Main bridges and roads.
3. Retaining walls.
Step 3 – 30% of total work
• Works within each cove:
1. Villas
2. Pool
3. Landscaping
Most Recent Updates
Step 1
• All reclamation and soil improvement works to enable construction of the committed villas is completed.
Step 2
• On Coves A & P main utility works in progress.
• The Bridge connecting PJA Trunk with Spine started and scheduled for completion by April 2009.
Step 3
• Detailed Design in progress.
• Construction of Palm Cove Townhouses is scheduled for completion no later than December 2012. |