Palm Jebel Ali
click on photo to view Palm Jebel Ali gallery

Palm Jebel Ali Town Houses

Background

The Town Houses of Palm Jebel Ali are located on coves of the fronds which provide each property sea view with a spacious section of waterfront.

Construction Process

Step 1 – 40% of total work
• Reclamation, soil improvement and breakwaters (key element of the development enabling the rest of the project to start).

Step 2 – 30% of total work
• Infrastructure works which includes:
1. Main utility services (electricity, water, sewage, telecom and gas).
2. Main bridges and roads.
3. Retaining walls.

Step 3 – 30% of total work
• Works within each cove:
1. Villas
2. Pool
3. Landscaping

Most Recent Updates

Step 1
• All reclamation and soil improvement works to enable construction of the committed villas is completed.

Step 2
• On Coves A & P main utility works in progress.
• The Bridge connecting PJA Trunk with Spine started and scheduled for completion by April 2009.

Step 3
• Detailed Design in progress.
• Construction of Palm Cove Townhouses is scheduled for completion no later than December 2012.