Palm Jebel Ali Water Homes
Background
504 Water Homes (252 Water homes at each crescent A&E) – raised on platforms above the waters of the Arabian Gulf with their own optional private leisure boat berths.
Construction Process
Step 1 – 20% of total work
Marine works, causeways reclamation works, protective breakwaters (all these form the key elements of the development enabling the rest off the project to be built on)
Step 2 – 50% of total work
Infrastructure and utilities, piles and platform (foundation for the Water Homes and elevated walkway) and causeway bridges (connecting Water Homes causeway and Crescent).
Step 3 – 30% of total work
House component and landscaping
Most Recent Updates
Step 1 at both Crescent A & E completed
• Marine Works
• Reclaimed causeways
• Breakwaters
Step 2
Generally the infrastructure and utilities works, piles and platforms and causeway bridges works for the development have commenced.
Specific information as follows:
At crescent A
• Infrastructure and utilities works started
• Piles and platforms works in progress
• Causeway bridge construction work in progress
At Crescent E
• Piles and platforms work started
Step 3
• Detail design of the Water Homes house component completed
• Pre-qualification of specialist timber builders completed. Contract for house component expected to be awarded early 2010.
• First batch of Water Homes due for completion during the second half of 2011 and the balance of the Crescent A Water Homes is scheduled for completion during 2012. |